
RM DUPLICATION SECTIONS 1-4 - NELSON


DURATION
Dec 2023 – Current
CLIENT
Nelson City Council
CONSULTANT/DESIGNER
Beca
VALUE
$4,040,000.00
Hunter Civil was engaged by the Nelson Regional Sewerage Business Unit (NRSBU) to rehabilitate a 1.4km section of an existing abandoned wastewater line. The purpose of the project was to increase the capacity and resilience of the regional sewer network. The pipeline conveyed raw wastewater from the Beach Road Pumpstation through to the Bell Island Treatment Plant.
The scope of work was varied and included both the laying of new sections of 560mm dia PE pipe and re-lining other sections of the existing abandoned 450mm dia asbestos concrete line. Two specialist subcontractors were engaged to complete the lining of the existing pipeline. There was a section of Structural Liner under State Highway 6 and Non-Structural Liner under the estuary. This lining technology was relatively new in New Zealand and the South Island with all materials being sourced from offshore.
Hunter Civil completed the sections of new pipeline and provided all the sheet piling and temporary works and access pits for the lining works. These pits varied in depth from 3 - 5m and needed to be completed in both private property, local roads, the estuary, and reserve land. Hunter Civil also completed all the traffic management, air & scour valve installation and reinstatement works.
One of the other requirements of this project was that the Great Taste Trail Cycleway crossed through the work site in several locations requiring specific management of the users of this track. Additional work was completed by Hunter Civil to realign a section of the cycleway to improve the track alignment long term and to allow easier diversion of the track during the construction works.